Adding resources without decreasing the duration of a task in Project

Read this tip to make your life smarter, better, faster and wiser. LifeTips is the place to go when you need to know about Project 98 and other Software topics.

Add additional resources to a task without decreasing the duration?

Adding resources without decreasing the duration of a task in Project

When you add a resource to a task, Project's default action will be to reduce the duration of a task (in proportion to the number of resources added). If you want to keep the duration the same (and therefore increase the work), you must change the task type to fixed duration.

Select the task and bring up the task information dialog box (Shift F2), click on the Advanced tab and select fixed duration from the task type box.

   